Closed-Loop Bioremediation Pilot Demo NWIRP Bethpage, NY

Project: Closed-Loop Bioremediation Pilot Demo NWIRP Bethpage, NY

Description: Bioremediation of Fuel Oil Impacted Soil and Groundwater

Role: Project Manager & Prime Contractor

Project Cost: $1.6 million (performance based)

Property impacted by a underground storage tank release of fuel oil #4, #6, and diesel.

Project Involved installation of the closed loop bioremediation system, 30 nested injection and extraction wells with a central control manifold.

Floating free product removal currently in progress.

Bioremediation system expected to be operating for 12 months.

Project started in August 2004 and is on-schedule for completion in March 2006.